Page 33 - English 01-15 March, 2026
P. 33

Pragati Platform | COVER STORY



                                                                           PROJECT

                                                                2.5 MMT Padur Strategic
                                                                     Crude Oil Storage


                                                             Sanction Date         PRAGATI Date
                                                             Jan 7, 2004           April 22, 2015,
                                                                                   March 23, 2016

                                                             Hurdles: Right-to-use and right-of-way-related issues

                                                             Cost                   Completion date
                                                             ₹7,581 crore          December 31, 2018


                                                                   The commissioning of the Padur SPR has
                                                               Benefits  not only brought socio-economic benefits but

                                                                   also strategic importance. It has strengthened
                                                                   India’s ability to respond to crude oil supply
                                                                   disruptions and emergencies.




                         PROJECT
                                                                             PROJECT
                  Kudankulam-APP

               Transmission System                                     Bembla Irrigation

                                                               Sanction Date         PRAGATI Date
        Sanction Date         PRAGATI Date                     April 2, 2007         October 25, 2023
        May 12, 2005          November 4, 2015
                                                               Hurdles: Land acquisition, financial issues
        Hurdles: Right-of-way and right-of-use issues,
        among others                                           Cost                     Completion date

        Cost                      Completion date              ₹2,685.41 crore         June 30, 2025
        ₹2,577.23 crore          Dec 31, 2019
                                                                     This project has reduced agricultural
              Improved power grid reliability and energy          Benefits  uncertainty in a drought-prone area.
          Benefits  security by promoting clean nuclear energy and   dependence on rainfall has decreased. n
                                                                     Cropping intensity has increased, and
              reducing costly power purchases. Supported
              India’s carbon reduction goals, while also
              boosting regional economic development and
              enhancing community confidence.












                                                                       March 1-15, 2026 || NEW INDIA SAMACHAR   31