Pragati Platform | COVER STORY




                                                    PROJECT


                     Saryu Nahar National Project

                    Completed after 4 decades






         Sanction Date          Project length: 318               lSince the project's inception, the cost has been
         Year 1978              km and linkages:                   revised 6 times. Delays in work have led to
                                6,590 km
                                                                   increased costs for construction materials, labour,
                                                                   and land acquisition.
         Irrigation      Inauguration                            lThe target for completing the project was set in
         Target: 1.4M   PM Narendra Modi                           1982 for 1988-89.
         hectares of    December 11, 2021
         land                                                    lIn 2014, when the government, led by Prime
                                                                   Minister Narendra Modi, began work, a review
                                                                   revealed that 99 major irrigation projects in the
           Hurdles  Lack of interdepartmental                      country had been incomplete for decades. The
              coordination and lack of proper
                                                                   Saryu Nahar National Project was among them.
              monitoring delayed the project.
                                                                 lAfter a review of projects pending for decades on
                                                                   the Pragati Platform, chaired by Prime Minister
                If it is government money, then why                Narendra Modi, obstacles facing the Saryu Canal
                should I care? This thinking had become            Project were resolved in a timely manner.
                the biggest obstacle in the balanced and         lOn December 11, 2021, Prime Minister Narendra
                all-round development of the country.              Modi inaugurated the Saryu Nahar National
                This thinking also kept the Saryu Canal            Project from Balrampur, Uttar Pradesh.
                project hanging. We have done more work
                in the Saryu canal project than what was         lThe project will benefit over 2.9 million farmers
                                                                   in nine districts of eastern Uttar Pradesh:
                done in 5 decades in less than 5 years. Our        Bahraich, Shravasti, Balrampur, Gonda,
                priority is to complete the project on time.       Siddharthnagar, Basti, Sant Kabir Nagar,

                Narendra Modi, Prime Minister                      Gorakhpur, and Maharajganj.
                                                                 lThe project was initiated at a cost of less
                                                                   than ₹100 crore. By the time the project was
                                                                   completed, its cost had increased to more than
                                                                   Rs 10 thousand crore.